ALBA storage ring reaches 100 mA

ALBA Synchrotron Light Facility
× close
ALBA Synchrotron Light Facility

The commissioning of the ALBA Storage Ring started on Tuesday 8th of March 2011 at 14:00h. Within one day the beam made few turns around the machine, and on the 13th of March, after switching on the RF, the beam was stored.

Three days later, the 16th of March, the beam was accumulated with parameters close to the nominal ones. This was confirmed by finding no difficulty coming from the 3 small gap (8mm) vacuum chambers already installed in the Storage Ring. After having tested all the machine protection system, on Friday 01.04.11 100 mA were stored on the storage ring.

This fast start-up has shown that the three accelerators (Linac, Booster and Storage Ring) are behaving as designed; and that all the different and numerous sub-systems have been properly installed and are working according to specs.

First image of the visible part of the synchrotron radiation spectra seen on the BL34-Xanadu diagnostics beamline
× close
First image of the visible part of the synchrotron radiation spectra seen on the BL34-Xanadu diagnostics beamline

The coming weeks will be dedicated to reach stable and reproducible settings, to measure the parameters of the accelerators in order to obtain the nominal settings, to correct the orbit, to increase the current and to clean the with synchrotron radiation.

In May, it is expected to test the first 3 Insertion Devices, two APPLE-II undulators and a normal conducting wiggler, which are already installed on the machine.

In the following there are some pictures and plots from the 16th of March 2011, a historical day for the ALBA project.

Provided by ALBA Synchrotron Light Facility

Load comments (8)

This article has been reviewed according to Science X's and . have highlighted the following attributes while ensuring the content's credibility:

Get Instant Summarized Text (GIST)

This summary was automatically generated using LLM.